Thursday, December 31, 2009

Construction Update #3

Not quite as busy this week, with Eldorado off for a holiday break. But here's a stitched-together view of the frame for the north bouldering wall.


Some electrical work has been done, and the ventilation ducts continue to snake their way around the ceiling. The other work of note is the steel frame going up to support the floor of the men's locker room.


Next week: Eldorado's back and their crew should grow to 10 workers. Work continues on the locker room structure, HVAC and electrical/lighting. And our staff arrive to start their new jobs, so we will be very busy planning the operations side of the business.